Have questions?
We’ve got the answers.
Interested in leasing your land but need to know more? Below are answers to the most common questions.
-
We usually seek a 40-year lease term. This provides a long-term, secure passive income for landowners and their future generations.
-
It depends. Many factors impact the price but solar farms typically receive £800-£1,100 per acre every year. Battery Energy Storage System (BESS) rents are around £1,500-£2000/MW per year.
-
Once planning permission is granted and we enter into the lease to start site construction. This is usually 12 months before the project becomes fully operational.
-
We usually allow for a 12 month construction period, but they are often shorter.
-
You can either enter into a new lease to continue your passive income, or have the land returned to its former agricultural state. If you choose the second option, all infrastructure is removed and recycled on your behalf.
-
It depends on the solar farm, but most of our projects produce between 15MW and 49.9MW. This is enough to power 5,000-20,000 homes.
-
Simply complete the form on the ‘Schedule a call’ page.